Skip to main content

Rapid Deployment For Erosion Prevention

RCR-12® | Drainage Pond Solution

Ground Prep Work for Drainage Pond

Anchor Trench

Seam Welding

ITL RCR® Installed

Project Objectives Using Reinforced Concrete Roll®

PROJECT OVERVIEW

Alpha Southwest chose to use ITL Reinforced Concrete Roll® in a drainage pond to explore the benefit of using a GCCM (Geosynthetic Cementitious Composite Mat) for rapid deployment and uniformity in place of traditionally poured concrete to prevent slope erosion.

PROJECT GOAL

Protect the surrounding slopes of a retention pond constructed for overflow.

RCR® AS A SOLUTION TO

  • Erosion on banks prior to installation.
  • Side wall failure & Stability issues.
  • Long-term and repeated repair cost.
  • Time & labor cost compared to traditional concrete pouring method.

Three Day Installation Using RCR® For Slope Protection

Compared to traditional concrete pouring methods, ITL RCR® was instrumental in armoring this retention pond in just three days.

Day One: Grading and trenching were performed utilizing 2' down and 1' back at the top and bottom of the slope.

Day Two: 75% of Reinforced Concrete Roll® material was deployed for the facing slopes.

Day Three: The remaining 25% of the material was installed, and the entire project was hydrated using a water truck with a pump. 

Comparatively, a local contractor estimated the project would take 1-2 weeks if traditional concrete methods were used.

Ask for a product sample or speak to one of our experts.


Leo Cortez | Product Manager

Cell: (509) 770-0602

Email: leoc@inlandtarp.com